Project Scope
Procurement, fabrication, testing and pre-commissioning of RO1 Process Module (slug catcher, hydrocylones, filters, pumps). |
Prefabrication at Blackheath workshop of upper box (35 tons), transportation to A Berth using special wide load truck, where main structure was being fabricated (100 tons).
Assembly using the harbour floating crane, painting, testing and pre-commissioning before load out on board installation vessel.
Total weight: 360 tons including:
- Structual steel = 138 tons
- Piping = 90 tons (30 tons duplex)
- Mechanical = 120 tons
- Electrical and Instrumentation = 12 tons
|  |
|