| Scope of Work
Fabrication and erection of steel structures and piperacks. Installation of equipment including reactors, vessels, pumps. Fabrication and erection of carbon and stainless steel pipework, blasting and painting, heat tracing and insulation. Electrical and instrument installation, testing and loop checking. Precommissioning.
Project Description
International engineering company Technip selected SA Five as main construction contractor for this project at PetroSA’s Mossel Bay Refinery. Mechanical, electrical and instrument field work was undertaken by establishment at PetroSA’s site.
Scope includes (approximate figures):
300 tonnes pipework fabrication and erection
500 tonnes structural steel fabrication and erection
200 systems for testpacks
5000m² piping insulation
1000m² vessel insulation
Major lifts include: Reactor (100T) and Catalyst Vessel (90T) |